The manhole that wasn't there
What an owner's site team protects while a ship is being built.
2026-09-28 · 11 min · Construction · LNG · Governance

Take three sister ships, all from the same set of drawings. Each one was to have a large seawater intake pipe with an inspection manhole as per the plans. Two of them did. The first one did not. For years it went unremarked. Superintendents and crews would go back and forth between the three vessels but never gave this detail a second thought; there was no cause to suspect any variance. Only when the time came to inspect the pipe on the first ship did the oversight come to light.
With no manhole to gain entry from within, the options were cumbersome: have divers go outside the hull to blank off the sea suction so the line could be opened, or put in for a drydock. A small matter overlooked at the yard and in the inspection process. Every operator can tell you about something similar: a valve that is only accessible once another piece is taken out, a machine put in where it cannot be reached, a design decision that defies explanation on board. The industry is full of such things.
What a missed detail costs
There are larger examples. SK Serenity and SK Spica, two 174,000 cubic meter LNG carriers fitted with the new KC-1 cargo-containment system, were put to sea in 2018. Defects in the cargo holds were soon found and operations stood down. By December 2023 an arbitration tribunal in London had made Samsung Heavy Industries pay in excess of US$290 million for damages.1 This was more than an inspection error; it called into question the design of a novel system. But the lesson for construction is plain: a technical problem is one thing to handle while the ship is under way in the yard, quite another once she is delivered.
Then there was the RRS Sir David Attenborough. Handed over in December 2020, the vessel was involved in an incident three months later when its port lifeboat came off the davits during a familiarization drill, leaving three crew with minor injuries. The UK Marine Accident Investigation Branch determined the installation did not meet the manufacturer’s spec, yet it had been approved. The ship had to go back to the builder to put things right.2
The survey work is instructive. MAIB concluded that a thorough safety-equipment survey ought to have shown the incomplete installation. They also noted a defect had been put on record and then closed once the davits were commissioned, with none of the parties in quality assurance or certification making an issue of it before acceptance. It was not just the owner’s site team at fault; operating and maintenance factors were in play too. The point is that an installation can get past construction and commissioning with something amiss.
The US Government Accountability Office has seen the same in naval shipbuilding: defects tend to show their face shortly after delivery, by which time the ship is in operation.3 That is of commercial consequence.
Consider Star Polaris, a bulk carrier that had a major engine failure some seven months after being delivered. Under the terms of an amended SAJ contract there was a 12-month guarantee on material and workmanship. When the dispute came to it, the buyer was not only looking to have the defect repaired but also put in a claim for towage, agency, off-hire and a drop in value.4
Public shipbuilding contracts show why the distinction matters. One contract filed with the US Securities and Exchange Commission provided a 12-month guarantee for defects in material, equipment and workmanship, while expressly excluding consequential loss, loss of time, profit and earnings.5
A defect may therefore remain the builder's responsibility while much of the operational consequence falls elsewhere.
That is one reason construction matters so much.
Three parties, different jobs
To an outsider, an owner’s site team at a yard might seem superfluous. The yard is putting the ship together and a classification society is on hand to survey it. What is the need for the buyer to have people there?
The roles are not the same. The builder is bound by contract to deliver the vessel to spec. Class will review the design and give reasonable assurance of compliance with its rules, and may do statutory work if the flag administration allows.6
The buyer’s representatives are there to look after the buyer’s side of the bargain. They put their eye on the drawings, they are present for the agreed tests, they note non-conformities and see to their correction. A contract filed with the SEC is clear on this: it makes provision for both class and a buyer’s supervisor, granting the latter access to the machinery and subcontractors, and stipulates that the builder is not absolved of his obligations by the approval of the buyer or class.5
They may overlap in function but they are not interchangeable.
Absence is a form of consent
There is an old adage that absence is a form of consent. A drawing review may seem like mere administration until the deadline has passed and it is not.
Take the shipbuilding contract on public file. The buyer was given fourteen days to put their approval or comments on the plans and drawings in question. If they did not respond, the drawings were automatically approved.5 The sea-trial provisions were no less straightforward. Advance notice was to be given to the buyer and its supervisor. Should the buyer’s side fail to show and put off the trial for more than a week, they were considered to have waived their right to be on board. The yard would then go ahead with class in attendance and follow the contractual certification process.
One can see the practicality in the legal wording. A manhole does not materialize in a pipe simply because all parties meant for it to be there; someone has to make the check.
Who speaks for the buyer
Then there is the matter of who is speaking for the buyer. The yard should not have to guess at every meeting who has the authority to do so. A project will have the owner, the technical manager, the charterer, financiers, class, flag, designers and consultants all involved. Their interests might be one and the same but their authority is not. The buyer must make clear who is empowered to comment, to accept or to order a change and what requires a call back to shore management.
Public contracts are explicit about this. The buyer puts in writing the appointment of a representative and the scope of his authority. In one instance, the builder was notified that the supervisor could only negotiate specification modifications to the extent the buyer had already authorized.5
Such discipline is essential when you are building sister ships. What was ascertained on Hull 1 should not have to be rediscovered on Hull 2.
Boring on purpose
For the most part, good newbuilding supervision is uneventful. It is boring by design.
The representative is not on site to have arguments with the yard or to make a contractual issue of every difference of opinion and report it back to shore. Consistency is the name of the game.
A non-conformity is put to rights against the spec, the yard responds, the record is closed and on you go. Shore management wants facts to act on, not atmosphere.
Years later, nobody operating the ship will care who wrote the sharper email during construction. They will care whether the equipment works, whether it can be maintained and whether the ship was built as specified.
New technology raises the stakes
New technology changes the dynamic. A newbuilding makes choices in propulsion, cargo systems and automation that will stand for decades before the full impact is felt in service.
Some systems come with a long history, others do not. The SK Serenity and SK Spica were the first to have the KC-1 containment system. The protracted dispute and defects that followed are not an argument against new tech, but for closer scrutiny where operating experience is thin.1
New technology does not deserve less challenge because it is new; if anything, fewer of the questions have been answered in service.
The last job
In the end, the manhole was on the drawing the whole time.
What was missing was the connection between the drawing and the steel on the first ship, and later the connection between what had been learned on one sister and what should have been checked on the others.
Over the course of a newbuild the site team accumulates information that the final drawings will never fully contain.
Why a deviation was accepted.
Why a test was repeated.
Which item caused trouble during commissioning.
What was changed on the first ship.
What still needs watching on the second.
That record has a commercial use. If a defect appears during the guarantee period, the owner's contemporaneous inspection, test and correspondence records may matter.
It has an operational use too. A ship can be delivered with drawings, manuals, certificates and test records and still arrive without much of the reasoning behind the decisions that shaped it. That reasoning lives, for a time, in people.
Passing it to the crews who will operate the ship, to the shore team that will support it and to the people building its sisters is the last job of the build. And the easiest to neglect.
Notes
- 1.Brick Court Chambers, 26 January 2024. A London tribunal ordered Samsung Heavy Industries to pay more than US$290 million over cargo-hold defects on SK Serenity and SK Spica, the first LNG carriers with the KC-1 containment system.
- 2.UK Marine Accident Investigation Branch, report 6/2023, on the lifeboat davit failure aboard RRS Sir David Attenborough.
- 3.US Government Accountability Office, Navy and Coast Guard Shipbuilding, GAO-16-71. Defects often become evident shortly after delivery.
- 4.Norton Rose Fulbright, on Star Polaris LLC v HHIC-Phil. Engine failure about seven months after delivery. The buyer claimed repair plus towage, agency, off-hire and a loss of value, under an amended SAJ contract with a 12-month guarantee.
- 5.A shipbuilding contract filed with the US Securities and Exchange Commission. Twelve-month guarantee for defects in material and workmanship, excluding consequential loss, including loss of time, profit and earnings. The same class of filing sets out the buyer’s supervisor, drawing approval, and sea trials.
- 6.International Association of Classification Societies, on the role of class.
Continue
Ambition and the Paths We Build
At the end of 2005, in the old Angolan House of Laws, I was asked by a future president what I wanted to be.
The transition happens to systems already running
Energy has to keep moving while the system changes. The transition happens to what is already running. It is not a replacement.